Cleco Caneland Substation
230kV-138kV Sub
This project was an EPC contract for a new 230kV-138 kV substation, involving complete greenfield civil site development, compaction, drainage, access roadway, and site limestone cover. We provided partial material procurement, the installation of all civil foundations and secondary containment, masonry control building and internals, structural steel erection, installation of breakers, switches, PTs, CCVTs, aluminum bus, insulators, lightning protection system, fiber-optic connectivity, all grounding, pre-cast trench, conduit duct-bank system, power and control cable, terminations, site lighting, and fencing/gates.
E.P. Breaux Utility Services provided complete construction services and materials management for the substation as a turn-key package.