Burns & McDonnell Temple Data Center
138kV/34.5kV substation
This project involved the construction of a new 138kV/34.5kV substation. E.P. Breaux Utility Services erected all structural steel and installed all owner-provided material. This included SF6 breakers, switches, arresters, capacitors, metering equipment, complete low side bay, MV power/control cable with terminations, aluminum bus, jumper connections, and lightening protection system.
E.P. Breaux Utility Services provided labor, hauled and managed owner-furnished material, issued the construction schedule, coordinated with other subcontractors, and provided a dedicated third-party safety employee.